Our Projects
-
Riser Pipe
Triad teamed with Traylor Industrial to fabricate and install new riser pipe sections for the Cooling Tower Replacement Project at Evaptech’s Fort St. Vrain Station in Platteville, Colorado. The pipe diameters varied from 42 to 68 inches including numerous branch and reducer sections. Our total production time to completion was three months. Traylor Industrial was…
-
Balustrades and Handrails
Triad is anticipating completion by the end of the year on the fabrication of nearly 11,000 feet of balustrades and handrails for Shimmick/Traylor/Granite Joint Venture on the Airport Guideway and Stations Design-Build Contract in Honolulu, Hawaii. These stainless-steel architectural balustrades will be used at four of the stations on the project and serve as another…
-
API-650 Storage Tanks
Triad fabricated and delivered two 12’-0” Dia. X 14’ tall API-650 storage tanks. This project was unique in the fact that these tanks had a highly technical fiberglass lining that had to be installed prior to delivery to the job site, with a very tight deadline to meet. Triad partnered with a local coatings contractor…
-
Howard Frankland Bridge
Triad was selected to fabricate approximately 1200 tons of pile templates for the Howard Frankland Bridge project in Tampa, FL. The project had a very aggressive schedule and required value engineering to facilitate assembly utilizing bolted connections as opposed to field welded connections. Triad added additional value to the project by utilizing our parent company’s…
-
Coal Gasification
Triad successfully executed a contract to fabricate and deliver all of the high-pressure injector nozzles that were used in a coal gasification plant that was built in Incheon, South Korea. Many of the components required were not “off the shelf” items and had to be manufactured in-house from a variety of alloy materials, such as…
-
Air Quality Control System
Triad was selected as the fabricator to supply Air Quality Control System components for a coal-fired power plant in Kentucky. Triad fabricated three units of Hastelloy C-276 scrubber tower caps along with the internal wall rings and support trusses. The external beam, angle, and channel stiffeners were all fabricated from 304 stainless steel. All of…